CS615 - Software Project Management Quiz No. 1 DEC, 04, 2012 Software design is actually a multi step process that focuses on _______ distinct attributes of a program 2 3 4 5 When you build a product or system, it's important to go through a series of predictable steps – a road map that helps you create a timely, high-quality result, The road map that you follow is called a __________ Software design Software Process Software schedule Framework The check-in and checkout facilities provide___________ Best control Component control SCI control Synchronization control Which of the following might require re-baselining of the cost baseline? Corrective action Revised cost estimates Updates to the cost management plan Budget updates Once the review is complete, the Software Requirements Specification is "signed-off by _________ Developer Customer Top level Management Both Customer and Developer. REF:: Once the review is complete, the Software Requirements Specification is "signed- off by both the customer and the developer. Controlling Versions is activity of ________ Construction Testing SCM Design ________ identify which quality standards are relevant to the project and determines how to satisfy them Quality planning Quality assurance Quality control Process control The British Standards Institution (1986) has stated the quality as The ability of a software product to satisfy its specified requirements "An inherent or distinguishing characteristic or a property" "Quality is in the eye of the beholder, a matter, of the client's judgment." All of the given ________ ensures that the standards laid down for a project are followed. Quality assurance Quality control Product evaluation Process control ________ ensures that appropriate steps to follow the product development procedures are carried out Quality Management Design Process monitoring Quality Control These all are Product Revision Factors except Usability Maintainability Flexibility Testability To control versions, you can use_____________ Version Control File Version Control Register Version Control authority All of given _________is an umbrella activity that ensures conformance to standards and procedures throughout the SDLC of a software product. SQA Design Testing All of given All of the following are benefits of meeting quality requirements An increase in stakeholder satisfaction Less rework Low turnover Higher productivity The Preliminary Users Manual presents the software as a black box: That is, heavy emphasis is placed on User input User output User input and the resultant output None of given Which of the following might require re-baselining of the cost baseline? Corrective action Revised cost estimates Updates to the cost management plan Budget updates ________ identify which quality standards are relevant to the project and determines how to satisfy them Quality planning Quality assurance Quality control Process control The overall role of Software in a larger system is identified during Overestimated savings from reusable components and new tools and methods Switching tools in mid-way Integrating different software products in cross-platform implementation You can use the Item Traceability Matrix to identify _______ at the end of each phase SCIs SCM Design Construction Most software project manager's practice a lot of management techniques that are of doubtful authenticity are called Select correct option: Project management tools Project management myths Project management thumb rules Project management fundamentals The Introduction of the software requirements specification states the Select correct option: Goals Objective Design Goals and objectives of the software The code generation step performs the task Select correct option: Translated specification into a machine-readable form Translated design into a machine-readable form Translated requirements into a machine-readable form Translated user data into a machine-readable form -----------is the ability to encourage by "push or pull" technical people to produce to their best ability. Select correct option: Evaluating Motivation None of the given Monitoring __________contains an analysis of what went wrong, what went right, and what you could have done better in the software project. Select correct option: Prepare closedown report Identify learning Identify reusable software components Finally, the specification includes a ________ Select correct option: Bibliography Appendix Both Bibliography and Appendix Product quality depends on its conformance to ______ Select correct option: Software requirements Development standards Implicit requirements All of given Given all are major design styles except Select correct option: Object (Not Sure) Procedural Structured Dtat-Structured Design The quality of software is said to be high if it meets the Standards, defined for the product Procedures, defined for the product Standards and procedures, defined for the product Design defined for product
Requirements engineering
Process engineering
System engineering
All of given
The British Standards Institution (1986) has stated the quality as
The ability of a software product to satisfy its specified requirements
"An inherent or distinguishing characteristic or a property"
"Quality is in the eye of the beholder, a matter, of the client's judgment."
All of the given
www.vuzs.net
McCall (MCC77) and his colleagues proposed some software quality factors based on _______ most important aspects of a software product:
4
3
6
5
Inefficient project management style is a
Product-related problems
Technology-related problems
Process-related problems
People-related problems
Upon evaluating current problems and desired information (input and output), the analyst begins to ______
Synthesize solutions
Model
Specification
All of given
These all are Product Revision Factors except
Usability
Maintainability
Flexibility
Testability
We can classify the problems that affect software projects into _______ categories
3
4
5
6
The check-in and checkout facilities provide_________
Best control
Component control
SCI control
Synchronization control
The code generation step performs the task
Translated specification into a machine-readable form
Translated design into a machine-readable form
Translated requirements into a machine-readable form
Translated user data into a machine-readable form
Research-oriented software development is a
Technology-related problems
Process-related problems
People-related problems
Product-related problems
A meeting is conducted at a _______ and attended by both software engineers and customers.
Software engineer site
Neutral site
Customer site
Company site
Reviews conducted at each of this phase/s_____
Analysis
Design
Coding
All of given
All given below are the problems that affect software projects except:
Product-related problems
Technology-related problems
Procedure-related problems
People-related problems
_______is the technical kernel of software engineering
Design
Implementation
Testing
Requirement Analysis
Both the software engineer and customer take an active role in software requirements engineering-a set of activities that is often referred to as
Analysis
Design
Specification
System acceptance
The model serves as the basis for the creation of ______ for the Software.
Design
Maintenance
Testing
Specifications
Before requirements can be analyzed, modeled, or specified they must be gathered through a/an _______
Elicitation process
Interviewing
Meeting
None of given
Technology-related problems include _____
All of given
Insufficient identification is a
Technology-related problems
Process-related problems
People-related problems
Product-related problems
Throughout evaluation and solution synthesis, the analyst's primary focus is on ______
"Not what, not "how"
"What, also "how"
"What, not "how"
None of given
The overall role of Software in a larger system is identified during
Requirements engineering
Process engineering
System engineering
All of given
In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.
Analyst
Designer
Coder
Manager
A 'facilitator' controls the meeting can be ________
Customer
A developer
An outsider
All of given
Version control combines ______ to manage different versions of configuration objects that are created during software product development.
Procedure
Tools
Procedure and Tools
None of given
Many software projects digress from the original scope because of the nature of the software product or technology used, it's happen in ________
Product scope changed toward the end of the project life cycle
Research-oriented software development
Defined scope
Fuzzy users
When you build a product or system, it's important to go through a series of predictable steps – a road map that helps you create a timely, high-quality result, The road map that you follow is called a ________
Software design
Software process
Software schedule
Framework
Before requirements can be analyzed, modeled, or specified they must be gathered through a/an _______
Elicitation process
Interviewing
Meeting
None of given
Defined scope is a
Technology-related problems
Product-related problems
Process-related problems
People-related problems
--
Ist woh jiss ney tumhari jeet ke Liye buhat kuch hara hoo
--
--
Virtual University of Pakistan*** IT n CS Blog
================================
http://www.eNoxel.com
http://www.enoxelit.tk
http://www.geniusweb.tk
and Please do Share this group with your Friends and Class Fellows so that our Circle would expand and can be more useful for other Students.
Thanks, n Best of Luck......
You received this message because you are subscribed to the Google
Groups "vulms" group.
To post to this group, send email to vulmsit@googlegroups.com
To unsubscribe from this group, send email to
vulmsit+unsubscribe@googlegroups.com
For more options, visit this group at
http://groups.google.com/group/vulmsit?hl=en?hl=en
---
You received this message because you are subscribed to the Google Groups "vulms" group.
Visit this group at http://groups.google.com/group/vulmsit?hl=en-GB.
--
Posted By Sheroo to **Virtual University Of Pakistan**Student Cafe at 12/04/2012 06:42:00 AM --
You received this message because you are subscribed to the Google Groups "VU Computer Science" group.
To post to this group, send email to vu-computer-science@googlegroups.com.
To unsubscribe from this group, send email to vu-computer-science+unsubscribe@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/vu-computer-science?hl=en.
0 comments:
Post a Comment